MAKMAL KESIHATAN AWAM KOTA BHARU

                                                                Document Number         : MKAKB/BP/QP-12
                             QUALITY PROCEDURE
                                                                Issue Number            : 01
                                                                Issue Date              : 03.04.2016
                        MANAGEMENT OF PERSONNEL                 Page Number             : 4 of 10

                       NO                          PROCEDURE                             RESPONSIBILITY

                      6.3.4    Conduct assessment as planned.                               LD/ HOU/ OIC

                               Verification of  staff competency should be based on
                               either internal or external testing.

                               a) Internal  testing for staff  competency  can  be  done
                               using :

                                  •  Direct  observation  of  routine  work  processes
                                      and  procedures  including  all  applicable  safety
                                      practices.
                                  •  Direct observation of equipment maintenance
                                      and function  checks.  Handling of  equipment
                                      should be evaluated based  on  capability to
                                      operate the specific equipment. The evaluation
                                      should be done by supervisory or authorized
                                      personnel.
                                  •  Monitoring  the  recording  and  reporting  of
                                      examination results.
                                  •  Review of work records.
                                  •  Assessment of problem-solving skills
                                  •  Examination of specially provided samples
                                      such  as  previously  examined  samples,  inter
                                      laboratory  comparison,  split  samples,  internal
                                      quality control samples and blind sample spike
                                      with a positive or negative control.

                               Supervisory or authorized personnel are responsible to
                               arrange the test and evaluate the test result of internal
                               testing.

                               b) External  testing of  staff competency is done by
                               participating in the proficiency  testing programs
                               provided by external agencies.

                                  •  The test result must be satisfactory and in the
                                      acceptable  range according to the each
                                      laboratory testing.
                                  •  Supervisory or authorized personnel are
                                      responsible to assign who should perform  the
                                      proficiency testing.













                    Disease Sector                                                          Quality Procedure
                                                 CONTROLLED DOCUMENT
   2   3   4   5   6   7   8   9   10   11   12